 |
"The Ground Heater
is excellent for curing because of its efficiency and short preparation time. We can run a
Ground Heater for seven days at about a cost of $200 per day."
Rick Koesel
|
| Ground Heater
"cures" winter construction woes Breckenridge,
Colo. Cold-weather construction is always challenging, no matter what the task. At
10,000 above sea level and an average snowpack of more than 70", winter
excavation and construction in Breckenridge, Colo., is virtually impossible. Challenged by
the complications of excavating frozen ground and concerns of cold-weather concrete
curing, many contractors shut down for the winter. For Towback Partners, a construction
company located in Breckenridge, shutting down was not an option in 1997.
Towback Partners had just begun work on a $9 million project in
Breckenridge in October 1996. The project, estimated to last 2 ½ years, involved the
construction of a 65-unit hotel/condominium complex known as The Corral. With limited time
allotted for completion of the job, Rick Koesel, construction manager of Towback Partners,
realized work would have to continue through the winter to remain on schedule. It was
while searching for a way to facilitate winter construction that Koesel discovered the
Ground Heater.
Recognizing the Ground Heaters potential to solve many
construction problems on The Corral and other jobs, Koesel decided to purchase the E3000,
the largest of the Ground Heater line, from Summit Equipment Rental Company in
Breckenridge.
"I realized that we would be running into these same construction
problems in the future, so I decided in the long run, buying a Ground Heater outright
would cost less than renting," Koesel said. He intended to use it not only for
thawing the ground, but also to facilitate proper concrete curing. Towback Partners took
possession of the E3000 in mid-January and immediately pressed it into service.
|
 Rick Koesel
Construction Manager,
Towback Partners
|
| Thawing Frozen Ground

Confronted with up to 7 of frost, Koesel first needed the Ground
Heater to penetrate the frozen ground. "Before installing footers or doing any
foundation work, we had to thaw the ground," Koesel said. "Normally, wed
have to wait until June to do any type of excavation work. Trying to excavate frozen
ground is like digging in concrete; you can hammer away all day and only take out small
chips of material."
To prepare for the thaw, Koesel and his crew removed the snow layer from
the foundation site. Next, they covered the area with the Ground Heaters heat
transfer hoses spread approximately 16" apart. The hoses were then covered with a
layer of polyethylene film to serve as a vapor barrier (this is important because moist
ground conducts heat 10 times faster than dry ground). The vapor barrier was covered with
3 layers of concrete curing blankets for thermal insulation. "The Ground Heater
worked great," Koesel said. "On an area roughly 4,000 sq. ft., we were able to
thaw 4 of frost in about 3 days and were ready to excavate. Without the Ground
Heater, winter excavation would be literally impossible."
|
. 1. The E3000 is equipped with 3,000' of heat transfer hose. It is the best
selling model of the Ground Heater line. |
| Concrete Curing

Koesels objective was to cure the poured wall to the "safe
stripping strength" required for "partial load, exposed surface." To attain
this required compressive strength, the wall had to be kept at 55° F for 5 days. Achieving this level of
compressive strength would then allow his crew to strip the forms and begin to load the
wall with no further concern of freezing temperatures or the need to apply additional heat
to protect the cure. He then made some assumptions about the relevant variable factors
including:
- Temperature of the concrete to be delivered to the site (75° F or higher).
- Average ambient outdoor air temperature forecasted for the cure period
(Koesel made sure sub-zero temperatures were avoided).
Koesel also determined and considered pertinent, non-variable factors
including:
- The mass of the concrete wall (315,000 lbs.).
- The specific heat of the concrete.
- The thermal efficiency of the concrete blankets to be used.
- The amount of "free" heat generated by the cement hydrating
into concrete.
- The amount of heat the concrete would lose when poured into the forms.
Koesel calculated that maintaining 55° F in the 315,000-lb. wall, including
forms, would require nearly the entire rated heat output of the E3000 Ground Heater
(300,000 BTUs/hour). Thus, he decided to operate the Ground Heater at its 180° F maximum temperature setting
rather than adjust it down. He got things off to a good, warm start by using the Ground
Heater to preheat the forms prior to the pour. Lastly, Koesel decided to cure the wall 7
days, rather than the minimum of 5 days, to provide a safety factor against exceptionally
low temperatures. "The Ground Heater only cost about $35 per day to run, so 2 extra
days is cheap insurance," Koesel explained.
|
. 2. Heat transfer hoses were strung on the wall forms using tie wire before
pouring concrete. |
| Executing the Cure

Before pouring concrete, the Ground Heater hoses were strung
horizontally in loops across both sides of the 150-long wall form sections. The
loops of hose were spaced approximately 1 apart on the form, from top to bottom, to
ensure uniform heating. The hoses were covered with concrete curing blankets and the
Ground Heater preheated the forms. 5 lifts were poured into the forms, using a
long-reach pump truck. Vibrating between each lift provided proper consolidation. Once the
entire 15-high wall section was poured, concrete blankets were placed over the top
of the forms and the Ground Heater continued to heat the newly poured wall. After 7 days,
the cure was complete and the forms were stripped.
|
. 3. Concrete was poured into the forms in five-foot lifts at a time, vibrating
between each lift to provide proper consolidation. |

"The Ground Heater is excellent
for curing because of its efficiency and short preparation time," Koesel said.
"Normally, wed have to use tube-type propane heaters to cure the concrete. That
involves a lot of time and money. We can run a Ground Heater for 7 days at a cost of about
$200, compared with propane heaters that would cost $200 per day." (A savings of
$1,200 per week!)
|
4. A long-reach truck was
used to distribute concrete at the site. To prevent freezing during transport, concrete
was delivered to the site at a temperature of 75º or higher. |

In addition, preparation time poses a
significant difference between the 2 methods. "With the Ground Heater, our set-up
time is cut in half, Koesel said. "We can set up the Ground Heater, blanket the wall
and be ready to pour in about half a day. On the other hand, using propane heaters
involves building tents over the walls. This is not only time consuming but inefficient as
well, because youre heating the air around the wall instead of heating the wall
directly."
|
5. Once the entire 15'-high
wall section was poured, concrete blankets were placed over the forms and the Ground
Heater continued to heat the newly poured wall. |
 Koesel plans to use the Ground Heater through May. "This is a big job, so
well continue to pour through spring and during the next two winters," Koesel
said. "Right now were using the Ground Heater about 15 out of every 30 days. It
has really become an essential piece of equipment for us."
So far, Towback Partners has only used the Ground Heater to thaw frozen
ground and cure formed concrete walls. "I can easily see using the Ground Heater to
cure slabs on grade, elevated slabs, columns
literally any type of concrete
placement," he said. "It really is a tremendous tool."
Go to Ground Heaters Surface and Air Heater Products Page
Go Back to the Job
Studies Page
|
6. The project, estimated to
last 2½ years,involves the construction of a 65-unit hotel / condominium complex know as
The Corral. |
|