|
As seen in ENR Magazine, March 9, 1998
|
|
Portable Radiant-Tube System Heats Up Concrete Construction
Slab-curing approach melts cold-weather work stoppagesBy William J. Angelo
|
|
| Some savvy contractors are taming
winter conditions by warming up to a patented radiant heat system that thaws frozen
ground, pre-heats forms and cures concrete in cold weather. The system has been used on
buildings and bridges alike, and proponents claim demand is so hot that sales may more
than double this year. To prove the year-round viability of tilt-up construction and
capitalize on an incentive clause, managers at St. Louis-based Clayco Construction Co.
Inc. used the system this winter on a $17-million, 550,000 sq. ft. concrete warehouse in
Tilton, NH. They successfully thawed frozen ground, poured a 2,700 ft. x 46 ft. casting
slab, and poured and cured 174 panels over a 10-week period between December and February
during sub-zero temperatures.
"In northern cities you dont see tilt-up construction because the perception
is that its strictly a summer product," says Robert G. Clark, president of
Clayco. "This will change our industry." The $250-million firm, which pours 6
million sq. ft. of wall a year, is purchasing five units at $48,000 each. "The rental
cost of the system was 75 cents per square foot," he adds.
Workers for C-T Concrete Co. Inc., Allentown, Pa., are using the system to build a
seven-story concrete flour mill in the states Pocono Mountains area.
"Were heating the floors as we go up, curing the concrete and also heating the
place," says Angelo W. Sorrentino, C-T president. For the jobs 12 in. thick
floors, the firm runs hoses 2 ft on center between two rebar mats. "We knocked off
about six hours a day in overtime for finish work," he says. "If the structure
was enclosed overtime would be minimal."
The closed and portable system,
manufactured by Ground Heaters, Inc., Spring Lake, MI., consists of a gravity flow
expansion tank, pumps and rubber hoses. Two models, a 150,000 or 300,000 BTU heater, can
cover up to 6,000 sq. ft. A thermostat controls heat, which ranges from 50° to 180° F. The
burners use 2.5 gallons of fuel oil per hour to heat biodegradable antifreeze that is
pumped through the system as low pressure. A compressor can blow the antifreeze out if
hoses are left in the pour.
When re-decking work on Chicagos Green Street Bridge
across the Kennedy Expressway was delayed until last December, managers for Kurtz
Construction, Inc., Burr Ridge, IL., opted for the heaters. After scarifying 6,000 sq. ft
of deck, the firm heated it for 24 hours at 180° F.
While the ambient air temperature hovered about 30°
F, the deck temperature remained at 55° F. "We
poured concrete the next morning, covered it with burlap, re-laid the hoses, covered them
with a vapor barrier and insulating blankets, and dialed the temp down to 50° F," says Douglas M. Nichele, ACCC project manager.
"Layout took four guys 20 to 30 minutes." He adds that the bridge opened to
traffic after a seven-day cure.
Sales of the units started slow in 1995, totaling only $285,000 but reached $3.5
million last year. "Our 98 pace is double last year" says Sue Meekhof, GHI
Vice President. Contractors "can configure the hoses any way they want: around
columns, protecting footings, or vertical poured walls," she adds.
Printable PDF version available here. |
|
|
| |
|
|
|
|
|